Sobha Developers Informing About the delays at the last minute

Hi Everyone here,
I share the same thoughts of those written in the posts here.
The project in which i booked the flat is already 1 year delayed and i am seeing another 6 month(minimum) delay. even at the 11th hour, these guys are not able to give the next expected date.

As per the sale deed, its a one sided agreement. If you make any mod, even shift a electrical point by one inch, you are not going to get the penalty promised for delayed delivery.

CRM has no decision making power, do not know whats happening in the project, do not know if project is understaffed etc… its just a front office just to make sure you don't hurl abuse over frustration direct to the site engineer or project director. If you ask to meet any higher ups, they will take you to CRM’s GM who is another ill informed fellow with no power.

So be prepared for delays and be cautious while going for Sobha Developers. I hope PNC reads this.